Work More Than Half Done To Open NC Ferry Channel

The contractor dredging the channel used for the Hatteras-Ocracoke ferry run is more than halfway done with the project.

A statement from the ferry division of the N.C. Department of Transportation said the contractor hired by the U.S. Army Corps of Engineers has removed 102,723 cubic yards of material to a required depth of 10 feet. The department said that amounts to 65 percent.

Operations on the Dredge Richmond were halted last Wednesday and Thursday due to high winds.

Shoaling in the channel has been an ongoing issue, but Hurricane Sandy, two back-to-back nor'easters and several winter storms have contributed to the problem. DOT has said it could be several weeks before the dredging takes care of the problem and the route returns to a normal schedule.


Comments are posted from viewers like you and do not always reflect the views of this station.
powered by Disqus

Current Conditions

Weather

Partly Cloudy

68°
Conditions at Pitt-Greenville Airport, NC
Weather

Overcast

69°
Conditions at New Bern, Craven County Regional Airport, NC
Weather

Mostly Cloudy

68°
Conditions at Washington, Warren Field Airport, NC
Weather

Partly Cloudy

71°
Conditions at Jacksonville, New River, Marine Corps Air Station, NC

Most Commented

powered by Disqus

Carolina Camera


Click one of the pictures below to see more or to upload your own photos and videos.

Special Sections

Search inventory from local dealers and private sellers.
Two minutes of info from local businesses.
Save 50% from local merchants.
Making Mom's Life Easier in Eastern Carolina.
Learn more about your Eastern Carolina's Experts.
Video tours to help you find your next apartment.
THE place to buy and sell items. Most ads free.