Work More Than Half Done To Open NC Ferry Channel

The contractor dredging the channel used for the Hatteras-Ocracoke ferry run is more than halfway done with the project.

A statement from the ferry division of the N.C. Department of Transportation said the contractor hired by the U.S. Army Corps of Engineers has removed 102,723 cubic yards of material to a required depth of 10 feet. The department said that amounts to 65 percent.

Operations on the Dredge Richmond were halted last Wednesday and Thursday due to high winds.

Shoaling in the channel has been an ongoing issue, but Hurricane Sandy, two back-to-back nor'easters and several winter storms have contributed to the problem. DOT has said it could be several weeks before the dredging takes care of the problem and the route returns to a normal schedule.


Comments are posted from viewers like you and do not always reflect the views of this station.
powered by Disqus
WITN

275 E. Arlington Blvd. Greenville, NC 27858 252-439-7777
Gray Television, Inc. - Copyright © 2002-2014 - Designed by Gray Digital Media - Powered by Clickability 189575501