New Bern Drawbridge Almost Done!

The New Bern Drawbridge that has been under construction for the past two and a half years is nearing completion.

This from DOT officials who say contractors have been testing the new drawbridge for the past 2 weeks.

The deadline for completion which had already been extended was December 12.

Contractor Balfour Beatty has filed for an additional three day extension that would send the project into the winter months phase.

This is when no liquidated damages can be collected by the state.

DOT Resident Engineer Johnny Metcalfe says the bridge is expected to be finished in about a month.

The winter months phase applies to all DOT contracts and runs from December 15th through March 15.


You must be logged in to post comments.

Username:
Password (case sensitive):
Remember Me:

Read Comments

Comments are posted from viewers like you and do not always reflect the views of this station.
  • by Todd Location: New Bern on Jan 11, 2010 at 06:32 AM
    As for the fish migration, that was well known during the original contract. It's no excuse for the delay that has helped to finish off several struggling downtown businesses and cost New Bern untold amount of tourist dollars.
  • by Bill Location: New Bern on Dec 29, 2009 at 01:37 PM
    This means BB could stretch this out until March 15 without penalty. The bridge will be done in "about a month"? What does that mean? Remember when it was going to be done in time for the 300th anniversary, which begins Dec 31?
  • by tug Location: New Bern on Dec 29, 2009 at 09:03 AM
    The reason it has taken so long is the state won't allow construction IN the water during certain months of the year due to fish migrations, spawning, etc. This bridge definitely could have been built faster if they were allowed to do it.
  • by Bob the builder on Dec 29, 2009 at 08:45 AM
    I agree Rocky,This contractor built the Manns Harbor Bridge and the state had the same problem with them then.
  • by Rocky on Dec 29, 2009 at 07:09 AM
    Sounds like the state should cross this contractor off their list for future projects. Is this December deadline that leaves out liquid damages self inposed by the state? rediculous!
  • by Me Location: Greenville, NC on Dec 29, 2009 at 06:46 AM
    It is absolutely ridiculous how long it has taken them to re-build this little bridge and now yet another delay.